BLUE HILLS 25MW
Contract Duration:
Mar 2004 / Oct 2005Scope:
Civil engineering, civil works and electromechanical erection of 2 x HRSGs, 1 x STG and BOP for a gas-fueled power plant expansion, originally composed of 2 frame 5 gas turbines. Scope included a commissioning & start-up assistance.