HOLCIM CEMENTO NACIONAL 1.1K tpd - LINE 1
Contract Duration:
Feb 1975 / Apr 1977Scope:
Electromechanical installation of a vertical clinker furnace (375 ton/hr). Furnace repair (120 tpd); mechanical erection of pre-heater, cicker press, cement separators Civil construction and electromechanical installation of complete line 1. Installation of pallet and sack lines.