CHILCA UNO 850MW

Chilca
Peru

Client:

POSCO E&C

Owner:

Enersur (GDF Suez)

Contract Duration:

Aug 2010 / Sep 2012

Scope:

Combined Cycle Conversion (CCC). Complete civil and electromechanical works for the Balance of Plant of (BOP) a CCC. The existing facility features 3 x Siemens gas turbines. Scope includes earthworks, concrete foundations, steel structures and buildings, 300 MW steam turbine and BOP equipment and tanks installation, piping pre fabrication and erection, MV and LV cabling and wiring, instrumentation and controls. Under contracto with DAEWOO ENGINEERING, now known as POSCO ENGINEERING, we are also building the associated pipeline and desalination plant.